Scalehouse & Road Relocation
Glendale Project #: 111219
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Barrel, Sahuaro, Yucca
Design Consultant:To Be Determined Department: LANDFILL
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
10/2012  100%  04/2013
Start CONSTRUCTION SCHEDULE Finish
  No Construction Phase   

Project Description:
Project includes relocation of scale house and other facilities supporting the landfill operation, including equipment maintenance area as well as administrative and field staff office trailers. Project also provides for realignment of internal entrance roadway and construction of asphalt-paved internal roadway to the new scale house location.

Project Status:
9-01-13: The final site assessment is complete. The professional services agreement is scheduled for Council approval on September 10th.The design phase will start after the agreement is approved. The RFQ for a Construction Manager at Risk contractor (CMAR) is currently advertising and the selection process should be completed by mid-October.


Schedule Variance Explanation: