A visual timeline of construction
Work kicks off for the downtown parking garage with soil test drilling. Jan. 2007
Ground is cleared to make room for the new parking garage. April 2007
Workers begin digging the below-ground portion of the garage.
The below-ground levels have been dug and workers build the retaining walls. Deep-sinking support beams are also poured to hold the above ground parking levels. June 2007
Support beams and the basement level of the garage begin to take shape. July 2007
The first floors begin to take shape. July and August 2007