Multi-use Pathway Grand Canal
Glendale Project #: 067005
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Yucca
Design Consultant:CH2M Hill Department: TRANSPORTATION
Project Contractor: No Contractor Selected

Start DESIGN SCHEDULE Finish
10/2009  100%  06/2014
Start CONSTRUCTION SCHEDULE Finish
08/2014  39%  12/2014

Project Description:
This project will construct a multi-use pathway from Bethany Home Road at Loop 101 along the Grand Canal to New River (107th Avenue).  

Project Status:
09-01-2013: ADOT has decided that they will administer the construction phase. The plans and specifications will need to be revised to the ADOT format, which will take several months. The project starts back at the 60% phase. The funding has been deferred to FY2014.


Schedule Variance Explanation: