Print
Multi-use Pathway Grand Canal
Glendale Project #: 067005
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Yucca
Design Consultant:CH2M Hill Department: TRANSPORTATION
Project Contractor: No Contractor Selected

Start DESIGN SCHEDULE Finish
10/2009  99%  05/2013
Start CONSTRUCTION SCHEDULE Finish
09/2013  0%  12/2013

Project Description:
This project will construct a multi-use pathway from Bethany Home Road at Loop 101 along the Grand Canal to New River (107th Avenue).  

Project Status:
04-01-2013: The 100% plans have been reviewed and the final comments are being addressed. All of the clearances have been approved accept for the Right-of-Way clearance, which is dependent on the approval of the agreement with SRP for the shared use of their maintenance road and the approval by the Federal Highway Administration (FHWA). This approval process may take another month or two.