WAWRF Slide Gates & Chain REplacemenys
|
|||||||||||||
Glendale Project #: 121309 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Tom Kaczmarowski | Council District(s): Yucca | ||||||||||||
| Design Consultant:GHD | Department: WATER / SEWER | ||||||||||||
| Project Contractor: Contractor Not Determined | |||||||||||||
|
|||||||||||||
Project Description: This project will use O & M funds to replace the rusted slide gates at the aeration basins, worn drive chains in the secondary sedimentation basins and repair / protect affected areas at the odor control facility containment slab. |
|||||||||||||
Project Status: 01-01-13: Project under planning stage. |
|||||||||||||
Schedule Variance Explanation: |
|||||||||||||