West Patrick Lane Drainage Canal Erosion Repair
Glendale Project #: 111223
CURRENT PROJECT SCHEDULE
Project Manager:Tom Kaczmarowski Council District(s): Cholla
Design Consultant:To Be Determined Department: FLOOD CONTROL
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
01/2013  100%  02/2013
Start CONSTRUCTION SCHEDULE Finish
04/2013  53%  06/2013

Project Description:
Project includes site repair, preparation, shotcrete/rip rap placement to repair eroded oufall to the new river.

Project Status:
01-01-13: Project under design.


Schedule Variance Explanation: