|
Scalehouse & Road Relocation
|
|||||||||||||
Glendale Project #: 111219 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Bill Passmore | Council District(s): Barrel, Sahuaro, Yucca | ||||||||||||
| Design Consultant:To Be Determined | Department: LANDFILL | ||||||||||||
| Project Contractor: Contractor Not Determined | |||||||||||||
|
|||||||||||||
Project Description:
Project includes relocation of scale house and other
facilities supporting the landfill operation, including equipment maintenance
area as well as administrative and field staff office trailers. Project also
provides for realignment of internal entrance roadway and construction of
asphalt-paved internal roadway to the new scale house location.
|
|||||||||||||
Project Status: 4-01-13: The final site assessment is complete and will be submitted for final review before April 4th. Once the final site assessment is approved the design phase could be started in late May/early June. |
|||||||||||||
Schedule Variance Explanation:
|
|||||||||||||