WAWRF Miscellaneous Improvements
Glendale Project #: 111213
CURRENT PROJECT SCHEDULE
Project Manager:Tom Kaczmarowski Council District(s): Yucca
Design Consultant:Malcolm Pirnie, Inc. Department: WATER / SEWER
Project Contractor: Hunter Contracting

Start DESIGN SCHEDULE Finish
02/2012  100%  04/2012
Start CONSTRUCTION SCHEDULE Finish
10/2012  100%  01/2013

Project Description:
This project entails ventilation design and improvements at the UV effluent channel, conceptual analysis & improvements of the existing Raw Sewage Pump Station (RSPS) and development of painting specifications & improvements at the West Area Water Reclamation Facility (WAWRF).

Project Status:
01-01-13: Construction 90% complete with final walk thru scheduled for the end of January 2013.. 


Schedule Variance Explanation: