Glendale Public Housing - Remodel Bathrooms
Glendale Project #: 111209
CURRENT PROJECT SCHEDULE
Project Manager:Mike Johnson Council District(s): Ocotillo
Design Consultant:To Be Determined Department: NEIGHBORHOOD IMPROVEMENTS
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
02/2012  100%  06/2012
Start CONSTRUCTION SCHEDULE Finish
10/2012  64%  10/2013

Project Description:
Provide labor and materials to remodel bathrooms in various apartment units in the Glendale Public Housing complex.

Project Status:

3-1-13:  As of to date, contractor have completed bathrooms at Cholla Vista #18, #26, Lamar #6101 and Glendale housing #6606. Glendale housing #5232 will be completed next week. Contractor will pull permits to start work on Cholla Vista #29, Lamar #6133 and Glendale #6604.



Schedule Variance Explanation: