COG Airport - Conair Property
Glendale Project #: 101107
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Barrel, Sahuaro, Yucca
Design Consultant:To Be Determined Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
12/2011  99%  05/2013
Start CONSTRUCTION SCHEDULE Finish
  No Construction Phase   

Project Description:

Project Status:
4-01-13: The FAA reviewed the preliminary environmental assessment (EA). The comments were addressed and the EA was re-submitted for the FAA's review and approval.


Schedule Variance Explanation:
2-01-13: Several divisions within the FAA have recently went through a re-organization process, which as affected the review of the revised environmental assessment (EA).