Fire Hydrant & Valve Replacement
Glendale Project #: 101130
CURRENT PROJECT SCHEDULE
Project Manager:Jim McMains Council District(s): Citywide
Design Consultant:In-House Department: WATER
Project Contractor: Sand Dollar Construction

Start DESIGN SCHEDULE Finish
01/2011  100%  02/2012
Start CONSTRUCTION SCHEDULE Finish
10/2012  100%  03/2013

Project Description:
This project will repair and/or replace numerous water valves and fire hydrants throughout the city.

Project Status:
03-05-2013: Fire hydrant and valve replacement is underway at various locations citywide.  Punch list items are being addressed by the contractor. Final completion is anticipated by mid-March.


Schedule Variance Explanation:
02-05-2013: A 28 day contract extension has been granted due to additional work requested by the city of Glendale Water Services Dept.  The new contract completion date is March 8, 2013