Downtown Alley Improvements
Glendale Project #: 091035
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Ocotillo
Design Consultant:Wood Patel & Associates Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
10/2010  100%  06/2014
Start CONSTRUCTION SCHEDULE Finish
08/2014  17%  12/2014

Project Description:
Design and construct transformation of existing service alley into a safe environment for pedestrian circulation and limited vehicular traffic.

Project Status:
09-01-13: The 60% design plans have been approved by ADOT. The Environmental Categorical Exclusion (CE) has been completed, but not yet fully approved by ADOT. Because of the delay caused by the expanded area for the cultural report the funding for this project has been deferred to FY 2014. Next steps include submitting 90% plans and getting approvals for the Right-of-Way and Utility clearances. These steps will take several months to complete. The APS project to underground the overhead utilities will start in early October.


Schedule Variance Explanation: