DOE UV Lamp and Well 43 Projects
|
|||||||||||||
Glendale Project #: 091033 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Mike Johnson | Council District(s): Cholla | ||||||||||||
| Design Consultant:Black & Veatch | Department: WATER / SEWER | ||||||||||||
| Project Contractor: MGC Contractors, Inc. | |||||||||||||
|
|||||||||||||
Project Description: This Project consists of design and construction of New high efficiency ultraviolet (UV) disinfection system and ancillary facilities at Arrowhead Ranch Water Reclamation Facility to save energy consumption and reduce operational cost. The Project also includes upgrade of electrical equipment at COG Well 43, a drinking water well owned by City of Glendale. |
|||||||||||||
Project Status: 3-1-13: Construction is still in progress. The UV building masonry work, roofing steel and the roof work are all completed. Next week the masonry contractor will be finishing up any detail work on the masonry blocks to the building. |
|||||||||||||
Schedule Variance Explanation: |
|||||||||||||