Arrowhead Blower Replacement
Glendale Project #: 091030
CURRENT PROJECT SCHEDULE
Project Manager:Mike Johnson Council District(s): Cholla
Design Consultant:Brown & Caldwell Department: WATER / SEWER
Project Contractor: Hunter Contracting

Start DESIGN SCHEDULE Finish
05/2010  100%  05/2012
Start CONSTRUCTION SCHEDULE Finish
07/2012  97%  05/2013

Project Description:

The control system at the arrowhead water reclamation facility blower building will be upgraded to enhance efficiency and reliability.


Project Status:

3-1-13: All the piping work to the project have been completed. The electrical contractor have completed all the conduit and wiring to the equipment and siemen's panels. The Siemen's tech. arrive on site this week to start installing the wiring into the siemen panels and start-up blower #1 on the new panel. Blower #1 will run for two (2) weeks prior to any work to began on blower #2.



Schedule Variance Explanation: