Glendale Airport Grant Projects
Glendale Project #: 091005
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Yucca
Design Consultant:To Be Determined Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
03/2010  100%  04/2012
Start CONSTRUCTION SCHEDULE Finish
03/2010  100%  04/2013

Project Description:

Project Status:
04-01-2013: All work, with the exception of the paving of the blast pads, has been completed. The paving of the blast pad test strips will be completed by April 5th. After the paving tests strips are approved the final blast pad paving will be completed.


Schedule Variance Explanation:

03-05-13: The airport runway must be closed during the paving operations and the night time temperatures are to cool to pave at this time. Spring training increases air traffic at the airport making day time closures impractical at this time.