Maryland Spot Improvements
Glendale Project #: 091003
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Yucca & Ocotillo
Design Consultant:CH2M Hill Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
10/2009  100%  01/2014
Start CONSTRUCTION SCHEDULE Finish
02/2014  54%  06/2014

Project Description:

This project will widen the roadway and add a bicycle lane on Maryland Avenue from 67th Ave to 69th Ave; connect Discovery Drive to Maryland Avenue just east of 80th Avenue via existing pathways in the park; and pipe a drainage channel 250 feet east of 75th Ave and build a paved multi-use path through the drainage alignment to allow bicycle and pedestrian access to 75th Avenue.  


Project Status:
09-01-2013: ADOT has decided that they will administer the construction phase. The plans and specifications will need to be revised to the ADOT format, which will take several months. The project starts back at the 60% phase. The funding has been deferred to FY2014.


Schedule Variance Explanation: