Print
New River Multi-use Pathway
Glendale Project #: 067006
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Yucca
Design Consultant:CH2M Hill Department: TRANSPORTATION
Project Contractor: No Contractor Selected

Start DESIGN SCHEDULE Finish
10/2009  100%  12/2013
Start CONSTRUCTION SCHEDULE Finish
02/2014  99%  07/2014

Project Description:
This project will construct a multi-use pathway along New River from Bethany Home Road to Northern Avenue. 

Project Status:
09-01-2013: The 100% plans are being revised to include the changes required by the Maricopa County Flood Control District (MCFCD). The plans have been submitted for MCFCD approval. After MCFCD approval the plans will be submitted to ADOT for one more review and if approved ADOT will schedule the bid advertisement.


Schedule Variance Explanation: