Multi-use Pathway Grand Canal
|
|||||||||||||
Glendale Project #: 067005 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Bill Passmore | Council District(s): Yucca | ||||||||||||
| Design Consultant:CH2M Hill | Department: TRANSPORTATION | ||||||||||||
| Project Contractor: No Contractor Selected | |||||||||||||
|
|||||||||||||
Project Description:
This project will construct
a multi-use pathway from Bethany Home Road at Loop 101 along the
Grand Canal to New River (107th Avenue).
|
|||||||||||||
Project Status: 04-01-2013: The 100% plans have been reviewed and the final comments are being addressed. All of the clearances have been approved accept for the Right-of-Way clearance, which is dependent on the approval of the agreement with SRP for the shared use of their maintenance road and the approval by the Federal Highway Administration (FHWA). This approval process may take another month or two. |
|||||||||||||
Schedule Variance Explanation: |
|||||||||||||