WAWRF Slide Gates & Chain REplacemenys
Glendale Project #: 121309
CURRENT PROJECT SCHEDULE
Project Manager:Tom Kaczmarowski Council District(s): Yucca
Design Consultant:GHD Department: WATER / SEWER
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
02/2013  100%  05/2013
Start CONSTRUCTION SCHEDULE Finish
08/2013  100%  12/2013

Project Description:
This project will use O & M funds to replace the rusted slide gates at the aeration basins, worn drive chains in the secondary sedimentation basins and repair / protect affected areas at the odor control facility containment slab.

Project Status:
09-01-13: Project advertisement on process.


Schedule Variance Explanation: