Print
Siphon at Grand Canal & Missouri Avenue
Glendale Project #: 121308
CURRENT PROJECT SCHEDULE
Project Manager:Tom Kaczmarowski Council District(s): Yucca
Design Consultant:Primatech, LLC Department: WATER / SEWER
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
03/2013  100%  06/2013
Start CONSTRUCTION SCHEDULE Finish
  No Construction Phase   

Project Description:
This project will investigate / evaluate current field conditions and provide recommendations for improvements to flow concerns at the 79th Avenue / Grand Canal sewerline interface. Evaluation will include analysis of existing design and improvement recommendations for consideration by utilities staff.

Project Status:
09-01-13: Project study 100% complete.


Schedule Variance Explanation: