Myrtle Avenue Safe Route to School Improvememnts
Glendale Project #: 121306
CURRENT PROJECT SCHEDULE
Project Manager:Tom Kaczmarowski Council District(s): Ocotillo
Design Consultant:To Be Determined Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
02/2010  100%  07/2013
Start CONSTRUCTION SCHEDULE Finish
12/2013  50%  08/2014

Project Description:
Project includes design and construction of drainage, sidewalks, ramps, driveways, street widening and realignment. as part of the ADOT Safe Routes to School Program. Project includes both eastbound and westbound Myrtle improvements. Utility poles will be relocated by APS to the north to accommodate the section.

Project Status:
09-01-13: Project is under design.


Schedule Variance Explanation: