Slurry Program 2012-2013
Glendale Project #: 121312
CURRENT PROJECT SCHEDULE
Project Manager:Jim McMains Council District(s): Citywide
Design Consultant:Ritoch-Powell Associates Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
11/2012  100%  01/2013
Start CONSTRUCTION SCHEDULE Finish
04/2013  87%  07/2013

Project Description:
This project includes surface preparation and repairs to prioritized residential streets by crack sealing, slurry seal and micro-seal applications.

Project Status:
03-05-2013  Southwest Slurry Seal will be awarded a construction contract for the 2012/2013 Slurry Seal Program at the March 26th Council meeting.  Start of construction is anticipated to be mid-April. 


Schedule Variance Explanation: