Solar Lighting Fixtures for Parks
Glendale Project #: 121311
CURRENT PROJECT SCHEDULE
Project Manager:Mike Johnson Council District(s): Citywide
Design Consultant:To Be Determined Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
11/2012  100%  12/2012
Start CONSTRUCTION SCHEDULE Finish
02/2013  100%  04/2013

Project Description:
Provide labor and materials to furnish and install fifty (50) solar light fixtures at various parks locations.

Project Status:

3-1-13:  Contractor have completed the pole foundations and have set all the solar poles in place at all eight (8) parks. The panels, light fixtures and batteries installation will be completed by mid-March.



Schedule Variance Explanation: