Print
COG Airport - Conair Property
Glendale Project #: 101107
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Barrel, Sahuaro, Yucca
Design Consultant:To Be Determined Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
12/2011  100%  12/2013
Start CONSTRUCTION SCHEDULE Finish
  No Construction Phase   

Project Description:

Project Status:
9-01-13: The environmental assessment (EA) is in the final stages and should be completed within the next few months.


Schedule Variance Explanation:
2-01-13: Several divisions within the FAA have recently went through a re-organization process, which as affected the review of the revised environmental assessment (EA).