Fire Hydrant & Valve Replacement
|
|||||||||||||
Glendale Project #: 101130 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Jim McMains | Council District(s): Citywide | ||||||||||||
| Design Consultant:In-House | Department: WATER | ||||||||||||
| Project Contractor: Sand Dollar Construction | |||||||||||||
|
|||||||||||||
Project Description:
This project will repair and/or replace numerous water
valves and fire hydrants throughout the city.
|
|||||||||||||
Project Status:
03-05-2013: Fire hydrant and valve replacement is
underway at various locations citywide. Punch list items are being
addressed by the contractor. Final completion is anticipated by
mid-March.
|
|||||||||||||
Schedule Variance Explanation:
02-05-2013: A 28 day contract extension has been
granted due to additional work requested by the city of Glendale Water Services
Dept. The new contract completion date is March 8,
2013
|
|||||||||||||