Print
Downtown Alley Improvements
Glendale Project #: 091035
CURRENT PROJECT SCHEDULE
Project Manager:Bill Passmore Council District(s): Ocotillo
Design Consultant:Wood Patel & Associates Department: TRANSPORTATION
Project Contractor: Contractor Not Determined

Start DESIGN SCHEDULE Finish
10/2010  96%  06/2013
Start CONSTRUCTION SCHEDULE Finish
09/2013  0%  12/2013

Project Description:
Design and construct transformation of existing service alley into a safe environment for pedestrian circulation and limited vehicular traffic.

Project Status:
04-01-13: The 60% design plans will be submitted before April 5th. The Environmental Categorical Exclusion (CE) has been completed and should be approved in April. Because of the delay caused by the expanded area for the cultural report a request to extend the approval process has been requested. The results of the extension request should be known before April 12th.


Schedule Variance Explanation: