|
Downtown Alley Improvements
|
|||||||||||||
Glendale Project #: 091035 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Bill Passmore | Council District(s): Ocotillo | ||||||||||||
| Design Consultant:Wood Patel & Associates | Department: TRANSPORTATION | ||||||||||||
| Project Contractor: Contractor Not Determined | |||||||||||||
|
|||||||||||||
Project Description:
Design and construct transformation of existing service
alley into a safe environment for pedestrian circulation and limited vehicular
traffic.
|
|||||||||||||
Project Status: 04-01-13: The 60% design plans will be submitted before April 5th. The Environmental Categorical Exclusion (CE) has been completed and should be approved in April. Because of the delay caused by the expanded area for the cultural report a request to extend the approval process has been requested. The results of the extension request should be known before April 12th. |
|||||||||||||
Schedule Variance Explanation:
|
|||||||||||||