DOE UV Lamp and Well 43 Projects
Glendale Project #: 091033
CURRENT PROJECT SCHEDULE
Project Manager:Mike Johnson Council District(s): Cholla
Design Consultant:Black & Veatch Department: WATER / SEWER
Project Contractor: MGC Contractors, Inc.

Start DESIGN SCHEDULE Finish
09/2010  100%  02/2012
Start CONSTRUCTION SCHEDULE Finish
07/2012  89%  06/2013

Project Description:

This Project consists of design and construction of New high efficiency ultraviolet (UV) disinfection system and ancillary facilities at Arrowhead Ranch Water Reclamation Facility to save energy consumption and reduce operational cost.  The Project also includes upgrade of electrical equipment at COG Well 43, a drinking water well owned by City of Glendale.


Project Status:

3-1-13: Construction is still in progress. The UV building masonry work, roofing steel and the roof work are all completed. Next week the masonry  contractor will be finishing up any detail work on the masonry blocks to the building.



Schedule Variance Explanation: