|
Arrowhead Blower Replacement
|
|||||||||||||
Glendale Project #: 091030 |
|||||||||||||
CURRENT PROJECT SCHEDULE |
|||||||||||||
| Project Manager:Mike Johnson | Council District(s): Cholla | ||||||||||||
| Design Consultant:Brown & Caldwell | Department: WATER / SEWER | ||||||||||||
| Project Contractor: Hunter Contracting | |||||||||||||
|
|||||||||||||
Project Description: The control system at the arrowhead water reclamation facility blower building will be upgraded to enhance efficiency and reliability. |
|||||||||||||
Project Status: 3-1-13: All the piping work to the project have been completed. The electrical contractor have completed all the conduit and wiring to the equipment and siemen's panels. The Siemen's tech. arrive on site this week to start installing the wiring into the siemen panels and start-up blower #1 on the new panel. Blower #1 will run for two (2) weeks prior to any work to began on blower #2. |
|||||||||||||
Schedule Variance Explanation: |
|||||||||||||